Company: CENX
Product Title: CENX
Product Version: V6.1
Frameworx Version: Version 16.0
Assessment Completion Date: January 2017
Detailed Certification Report: CENX Fx16.0 Conformance Certification Report V1.0
Business Process Framework Assessment Summary
TM Forum has reviewed and approved the self-assessment of the Product listed here against Business Process Framework (eTOM) version 16.0 processes elements. Each process element was measured using the Business Process Framework (eTOM) conformance scale.
Scope of Assessment – Business Process Framework Footprint
The following figures represent the Business Process Framework Level 2 processes (high-lighted in green) that were presented in scope for the assessment.
The following graph represents the Business Process Framework Level 2 processes that were submitted for the Assessment and the coverage of the Level 2 processes in terms of number of Level 3 processes submitted in scope.
Product Conformance Summary – Business Process Framework
The following charts give an overview of the conformance scores granted to the Business Process Framework Level 3 processes presented in scope for CENX Frameworx Conformance Certification assessment.
Product Conformance Detailed – Business Process Framework
The following table provides a detailed breakdown of the scores awarded with some additional commentary.
CENX V6.1 |
||
L1 / L2 / L3 Process |
L3 Process Score |
Comments |
Service Domain |
||
Level 2: 1.4.6 – Service Problem Management |
[4/7] |
|
1.4.6.1 – Create Service Trouble Report |
4.5 |
Partially Conformant |
1.4.6.2 – Diagnose Service Problem |
5.0 |
Fully Conformant |
1.4.6.3 – Correct & Resolve Service Problem |
Not in Scope |
This process was not submitted for assessment. |
1.4.6.4 – Track & Manage Service Problem |
Not in Scope |
This process was not submitted for assessment. |
1.4.6.5 – Report Service Problem |
Not in Scope |
This process was not submitted for assessment. |
1.4.6.6 – Close Service Trouble Report |
5 |
Fully Conformant |
1.4.6.7 – Survey & Analyze Service Problem |
4.8 |
Partially Conformant |
Level 2: 1.4.7 – Service Quality Management |
[4/7] |
|
1.4.7.1 – Monitor Service Quality |
5.0 |
Fully Conformant |
1.4.7.2 – Analyze Service Quality |
5.0 |
Fully Conformant |
1.4.7.3 – Improve Service Quality |
Not in Scope |
This process was not submitted for assessment. |
1.4.7.4 – Report Service Quality Performance |
Not in Scope |
This process was not submitted for assessment. |
1.4.7.5 – Create Service Performance Degradation Report |
5.0 |
Fully Conformant |
1.4.7.6 – Track & Manage Service Quality Performance Resolution |
Not in Scope |
This process was not submitted for assessment. |
1.4.7.7 – Close Service Performance Degradation Report |
5.0 |
Fully Conformant |
Resource Domain |
||
Level 2: 1.5.8 – Resource Trouble Management |
[4/7] |
|
1.5.8.1 – Survey & Analyze Resource Trouble |
5.0 |
Fully Conformant |
1.5.8.2 – Localize Resource Trouble |
5.0 |
Fully Conformant |
1.5.8.3 – Correct & Resolve Resource Trouble |
Not in Scope |
This process was not submitted for assessment. |
1.5.8.4 – Track & Manage Resource Trouble |
Not in Scope |
This process was not submitted for assessment. |
1.5.8.5 – Report Resource Trouble |
Not in Scope |
This process was not submitted for assessment. |
1.5.8.6 – Close Resource Trouble Report |
5.0 |
Fully Conformant |
1.5.8.7 – Create Resource Trouble Report |
4.5 |
Partially Conformant |
Level 2: 1.5.9 – Resource Performance Management |
[3/7] |
|
1.5.9.1 – Monitor Resource Performance |
5.0 |
Fully Conformant |
1.5.9.2 – Analyze Resource Performance |
Not in Scope |
This process was not submitted for assessment. |
1.5.9.3 – Control Resource Performance |
Not in Scope |
This process was not submitted for assessment. |
1.5.9.4 – Report Resource Performance |
Not in Scope |
This process was not submitted for assessment. |
1.5.9.5 – Create Resource Performance Degradation Report |
5.0 |
Fully Conformant |
1.5.9.6 – Track & Manage Resource Performance Resolution |
Not in Scope |
This process was not submitted for assessment. |
1.5.9.7 – Close Resource Performance Degradation Report |
5.0 |
Fully Conformant |
For more comprehensive results for the overall Assessment, please access the full Certification Report in the Downloads area below.
Downloads | Type |
---|---|
CENX Fx16.0 Conformance Certification Report V1.0 |
Report Misuse: Frameworx conformance is an important part of enabling the communications industry to maintain profitability as it migrates to new services and new business models. Gaining the conformance mark represents a significant investment by both suppliers and service providers. If you feel a company is misusing the conformance mark then please let us know at [email protected].
Disclaimer: TM Forum has conducted no independent testing of the solution for conformance with its frameworks or standards. Such testing has solely been conducted by the supplier or seller of the product and has been self-assessed by the supplier or seller for adherence to the TM Forum framework or standard in question. Accordingly, under no circumstances will TM Forum be liable for any direct or indirect damages or any costs or losses resulting from the use or reliance by any party of or upon such certification.